Applying building information modeling to integrate schedule and cost for establishing construction progress curves
Kun-Chi Wang, Wei-Chih Wang, Han-Hsiang Wang, Pei-Yuan Hsu, Wei-Hao Wu, Cheng-Ju Kung
1. Introduction
A cost-based progress curve (S-curve), which is a graphical representation of cumulative progress against time, is commonly used to control the schedule of a construction project. The vertical scale of an S-curve represents the cumulative project progress in dollars or as percentage completed, and the horizontal scale represents time. To plot an S-curve, the costs that are associated with each activity in the project schedule must be determined.
An accurate calculation of the cost of a scheduling activity depends on the identification of relevant cost items (cost centers or cost accounts) that represent the construction resources or physical end items (such as reinforced steel, form, and concrete) that are required to perform that activity. A cost item comprises the quantity and unit price of a particular resource. Each cost item may be associated with one or several activities. Accordingly, the cost of an activity is the required (distributed or allocated) quantity multiplying by the unit price of the cost item. Therefore, the total costs of the activity are the sum of the costs of the associated cost items (if the activity is associated with many cost items).
If only one cost item is relevant to the aforementioned cost calculation for an activity, then the relationship between the activity and the cost item is typically called a one-to-one relationship (because one activity is associated with one cost item). For instance, the activity of installing steel falsework commonly corresponds to a single cost item (steel falsework), resulting in a one-to-one relationship.
Other relationships, such as many-to-one or many-to-many, may exist between different types of activities and cost items. For example, the use of 280 kg f/cm2 concrete to grout the first, second, and third floor slabs exhibits a many-to-one relationship in which three activities correspond to one cost item (280 kg f/cm2 concrete). In this case, the cost of the 280 kg f/cm2 concrete cost item should be allocated to all three activities. In a many-to-many relationship, the activities of setting 1st-floor columns/walls steel and setting 1st-floor beams/slabs steel are both associated with the costs the two cost items - rebar SD420Wand rebar SD420. Although the above calculations can be carried out, it is highly time-consuming and error-prone, especially when a construction project involves hundreds of activities and cost items.
The above problem is often described as the problem of integrating schedule and cost. This problem basically arises from the fact that schedule- and cost-control functions are performed independently of each other and use different control structures: the work breakdown structure (WBS) and the cost breakdown structure (CBS). To reduce the complexity of integrating scheduling activities with cost items, many practitioners take the simple approach of using a master-level schedule that comprises only a few milestone activities to generate an S-curve. As an example, a milestone activity “structure construction” is used to represent many activities in detail, such as “layout”, “setting steel of column/beam/wall/slab”, “setting forms of column/ beam/wall/slab”, “concreting”, and others. The costs that are associated with this milestone activity are then easily obtained by summing the costs of the many associated cost items (including layout, steel, form, and concrete) without further breaking down the cost of each item into those associated with the individual activities. Although this simplified approach saves time, it reduces the accuracy of the curve. Conversely, using a detailed task-level schedule (instead of a milestone schedule) to obtain an accurate S curve considerably increases the workload associated with data acquisition and processing.
An accurate S curve sets a precise progress target (or the budgeted cost of the work scheduled) to be accomplished in a given time period, whereas a rough curve developed using milestone activities adds little value to the schedule control of a construction project. Developing a more accurate S curve requires more efficiently computing the costs of each activity.
The rapid development of information technologies has provided solutions to numerous construction management problems such as integrating design and construction activities and cost estimation. Recently, the building information model (BIM), which is a new IT and is a three-dimensional (3D) framework that can digitize a great amount
of building information, has attracted much attention owing to its effectiveness in data acquisition and storage in support of construction management. Notably, several researchers have developed BIM-based methods to extract quantities or estimate costs. However, these quantity takeoffs and cost estimations can only account for one cost item at one time. Accordingly, this study develops a method of using BIM to resolve the complicated relationships between schedule and cost to establish a construction S curve that supports schedule control.
2. Review of recent studies
This section reviews recent studies of construction progress curves, the integration of schedule and cost, the use of BIM for quantity takeoffs and cost estimation, and automated construction progress tracking.
2.1. Construction progress curve
An S-curve typically has a small slope at its beginning and near its end and a large slope in the middle, indicating that progress is slow in mobilization and demobilization periods, but faster as the bulk of the work takes place. The S-curve is widely used to control construction project schedules and is effective for reporting the status, and predicting the
剩余内容已隐藏,支付完成后下载完整资料
毕业设计
英文文献及翻译
姓 名: 周 璟 雯
学 号: 15200412130
专 业 名 称: 工 程 管 理
指 导 老 师: 祝 连 波
提 交 日 期: 2019年5月20日
Applying building information modeling to integrate schedule and cost for establishing construction progress curves
Kun-Chi Wang, Wei-Chih Wang, Pei-Yuan Hsu, Wei-Hao Wu, Cheng-Ju Kung
Department of Civil Engineering, National Chiao Tung University
1. Introduction
A cost-based progress curve (S-curve), which is a graphical representation of cumulative progress against time, is commonly used to control the schedule of a construction project. The vertical scale of an S-curve represents the cumulative project progress in dollars or as percentage completed, and the horizontal scale represents time. To plot an S-curve, the costs that are associated with each activity in the project schedule must be determined.
An accurate calculation of the cost of a scheduling activity depends on the identification of relevant cost items (cost centers or cost accounts) that represent the construction resources or physical end items (such as reinforced steel, form, and concrete) that are required to perform that activity. A cost item comprises the quantity and unit price of a particular resource. Each cost item may be associated with one or several activities. Accordingly, the cost of an activity is the required (distributed or allocated) quantity multiplying by the unit price of the cost item. Therefore, the total costs of the activity are the sum of the costs of the associated cost items (if the activity is associated with many cost items).
If only one cost item is relevant to the aforementioned cost calculation for an activity, then the relationship between the activity and the cost item is typically called a one-to-one relationship (because one activity is associated with one cost item). For instance, the activity of installing steel falsework commonly corresponds to a single cost item (steel falsework), resulting in a one-to-one relationship.
Other relationships, such as many-to-one or many-to-many, may exist between different types of activities and cost items. For example, the use of 280 kg f/cm2 concrete to grout the first, second, and third floor slabs exhibits a many-to-one relationship in which three activities correspond to one cost item (280 kg f/cm2 concrete). In this case, the cost of the 280 kg f/cm2 concrete cost item should be allocated to all three activities. In a many-to-many relationship, the activities of setting 1st-floor columns/walls steel and setting 1st-floor beams/slabs steel are both associated with the costs the two cost items - rebar SD420Wand rebar SD420. Although the above calculations can be carried out, it is highly time-consuming and error-prone, especially when a construction project involves hundreds of activities and cost items.
The above problem is often described as the problem of integrating schedule and cost. This problem basically arises from the fact that schedule- and cost-control functions are performed independently of each other and use different control structures: the work breakdown structure (WBS) and the cost breakdown structure (CBS).
To reduce the complexity of integrating scheduling activities with cost items, many practitioners take the simple approach of using a master-level schedule that comprises only a few milestone activities to generate an S-curve. As an example, a milestone activity “structure construction” is used to represent many activities in detail, such as “layout”, “setting steel of column/beam/wall/slab”, “setting forms of column/ beam/wall/slab”, “concreting”, and others. The costs that are associated with this milestone activity are then easily obtained by summing the costs of the many associated cost items (including layout, steel, form, and concrete) without further breaking down the cost of each item into those associated with the individual activities. Although this simplified approach saves time, it reduces the accuracy of the curve. Conversely, using a detailed task-level schedule (instead of a milestone schedule) to obtain an accurate S curve considerably increases the workload associated with data acquisition and processing.
An accurate S curve sets a precise progress target (or the budgeted cost of the work scheduled) to be accomplished in a given time period, whereas a rough curve developed using milestone activities adds little value to the schedule control of a construction project. Developing a more accurate S curve requires more efficiently computing the costs of each activity.
The rapid development of information technologies has provided solutions to numerous construction management problems such as integrating design and construction activities and cost estimation. Recently, the building information model (BIM), which is a new IT and is a three-dimensional (3D) framework that can digitize a great amount of building information, has attracted much attention owing to its effectiveness in data acquisition and storage in support of construction management. Notably, several researchers have developed BIM-based methods to extract quantities or estimate costs. However, these quantity takeoffs and cost estimations can only account for one cost item at one time.
Accordingly, this study develops a method of using BIM to resolve the complicated relationships between schedule and cost to establish a construction S curve that supports schedule control.
2. Review of recent studies
This section reviews recent studies of construction progress curves, the integration of schedule and cost, the use of BIM for quantity takeoffs and cost estimation, and automated construction progress tracking.
2.1.
剩余内容已隐藏,支付完成后下载完整资料
资料编号:[440373],资料为PDF文档或Word文档,PDF文档可免费转换为Word
您可能感兴趣的文章
- 饮用水微生物群:一个全面的时空研究,以监测巴黎供水系统的水质外文翻译资料
- 步进电机控制和摩擦模型对复杂机械系统精确定位的影响外文翻译资料
- 具有温湿度控制的开式阴极PEM燃料电池性能的提升外文翻译资料
- 警报定时系统对驾驶员行为的影响:调查驾驶员信任的差异以及根据警报定时对警报的响应外文翻译资料
- 门禁系统的零知识认证解决方案外文翻译资料
- 车辆废气及室外环境中悬浮微粒中有机磷的含量—-个案研究外文翻译资料
- ZigBee协议对城市风力涡轮机的无线监控: 支持应用软件和传感器模块外文翻译资料
- ZigBee系统在医疗保健中提供位置信息和传感器数据传输的方案外文翻译资料
- 基于PLC的模糊控制器在污水处理系统中的应用外文翻译资料
- 光伏并联最大功率点跟踪系统独立应用程序外文翻译资料
